What is the best way to apply and record costs for acceleration?
Asked 2 years ago
2021-12-13 06:58:38We are contracted to deliver a project by the middle of January, however I am forecasting this to run over by at least 5 months. We are increasing labour to keep up and I have issued an EWN to support this with no response from the customer, and requested a direct acceleration notification from them, with no response. The customer is condensing the programme instead of recognising the delay and extending the time to complete. The delay is not of our making, as we are last in. The contract itself is an NEC3, lump sum and I have enclosed the outtake on acceleration in the upload attachments.