Answers
Andrew Crawford
What delay analysis technique do you use?
Asked by Andrew Crawford, 6 months ago
Steve, if there is no accepted programme and never has been I think you must be free to utilise whatever approach best suits your case / your data. Yo ...
2 0
Andrew Crawford
What delay analysis technique do you use?
Asked by Andrew Crawford, 6 months ago
There are a number of points to you question.Looking first at the easiest part you refer to compensation event ('CE') which implies a NEC type contrac ...
5 0
Steve Hardy
What important points should I cover when striking a deal with my subcontractor to accelerate completion of his works?
Asked by Steve Hardy, 7 months ago
As the contract is a JCT Contract a key consideration is how you intend to instruct and implement the acceleration agreement. Schedule 2 contains prov ...
3 0
Sean Ruddy
Should a contract administrator issue a non-completion certificate under a JCT form of Contract knowing that it has not fully assessed all the EOTs?
Asked by Sean Ruddy, 7 months ago
I agree with Andrew, the simple answer is yes, but the Employer would be ill advised to try and deduct Damages in this scenario. I think the CA is bou ...
1 0