Parliament revamp urged to "avoid HS2 and Crossrail cost trap"
26 April, 2020
An article from Construction News on 24 April 2020 discusses the dangers of a single figure estimate for the budget.
Public-sector
Refurbishment
Lessons-learnt
Budgets
Citing Crossrail and HS2 as examples from which to learn, the NAO says the decision of delivery bodies to publish ‘firm’ commitments too early brought external pressure to meet those commitments at the expense of value for money. Decisions on Crossrail were influenced and dominated by fixed completion dates and costs, the NAO says, due to the fact estimates were published without information on the level of uncertainty within them.