Notice of Sub-Contractor Delay to the Sub-Contract Completion Date under the JCT Design & Build Sub-Contract 2016 [unamended]

3 July, 2020

Proforma Delay Notice from a Contractor to a Sub-Contractor who has failed to complete the Sub-Contract Works by the Completion Date

Delay

Contract notices

Sub-Contract Completion Date

Loss and Expense

Notice of Delay

This letter is issued pursuant to clause 2.21 and 4.17 notifying of your failure to complete the Sub-Contract Works within the relevant period for completion and as a result, its affect upon the regular progress of the Main Contract Works.............................................